E-Commerce Practicum |
Week |
Activity |
1 |
Form teams, receive client objectives |
2 | Develop plan of attack, conduct market research, interview client/users |
3 | Submit team Research and Interview Summary |
4 | Develop system requirements, plan integration of new system into existing business |
5 | Submit Requirements Document |
6-7 | Develop detailed system design, including needed organizational and procedural changes, along with cost/benefit, profitability and risk analysis. Submit draft design document for client/faculty review |
8 | Negotiate and submit final Design Document |
9-12 | Implement and document system. Deliver prototype for testing |
13 | Acceptance testing/debugging. |
14 | Hand off system to client. Submit final individual report analyzing success/failure and what was learned during the development process. |